Proper Mechanical Commissioning Cuts Whole-Building Energy Use by a Median of 13%, JDI Industrial Services Analysis Finds
Published
2 months agoon
By
Lawrence Berkeley National Laboratory studied 643 U.S. commercial buildings and found that structured commissioning during new construction pays for itself in under five years. Lawrence Berkeley National Laboratory (LBNL), U.S. Department of Energy — 2009
WESTMINSTER, S.C., June 25, 2026 /PRNewswire/ — JDI Industrial Services has released an analysis of federal and industry research examining one of the most persistent challenges in industrial and commercial construction: integrating new mechanical systems with existing facility infrastructure during turn-key projects.
Drawing on studies from the U.S. Department of Energy, Lawrence Berkeley National Laboratory (LBNL), Pacific Northwest National Laboratory (PNNL), and construction-industry research organizations, the analysis finds that coordination failures and poor system integration create billions of dollars in avoidable costs each year. At the same time, structured commissioning and controls optimization consistently deliver measurable returns through reduced energy consumption, lower rework costs, and improved operational performance.
The findings reveal a striking imbalance between the cost of integration failures and the cost of preventing them. According to the 2018 FMI Corporation and Autodesk Construction Disconnected Report, poor project data and communication account for 52% of all construction rework, resulting in approximately $31.3 billion in rework costs across the U.S. construction industry. The same report estimates that construction professionals spend roughly 35% of their working time, more than 14 hours per week, on non-productive activities such as searching for information, resolving conflicts, and correcting avoidable errors.
For facility owners undertaking turn-key mechanical projects, the implications extend far beyond construction schedules. Mechanical systems operate at the intersection of process requirements, building infrastructure, controls networks, utility services, and safety systems. When integration planning is incomplete, the resulting failures often emerge after equipment installation, when correction costs are highest and operational disruptions become unavoidable.
Mechanical Integration Failures Create Costs Before Systems Go Online
Mechanical integration problems rarely begin with equipment installation. Most originate during project planning, when incomplete documentation, poor coordination among trades, or insufficient understanding of existing facility conditions introduce risks that remain hidden until commissioning or startup.
According to the FMI Corporation and Autodesk Construction Disconnected Report (2018), construction workers spend approximately 35% of their time on non-productive activities, representing an estimated $177.5 billion in annual labor costs across the U.S. construction industry. Much of that lost time stems from locating project information, resolving conflicts between disciplines, and addressing work that must be corrected because of coordination failures.
For mechanical contractors, integration challenges often involve mismatches between new equipment and existing infrastructure. Electrical loads may differ from documented conditions. Building automation systems may require communication protocols that were not identified during design. Existing utility systems may have less available capacity than anticipated. Structural, process, and mechanical requirements may compete for the same physical space.
The analysis finds that these issues frequently appear during late-stage construction because integration planning is treated as a documentation exercise rather than a system-performance exercise. By the time problems become visible in the field, schedule pressure often encourages temporary workarounds rather than permanent solutions.
Industry research suggests that this approach creates a compounding cost effect. Every unresolved integration issue increases the likelihood of downstream rework, startup delays, performance deficiencies, and operational inefficiencies that persist long after construction is complete.
Rework Remains One of the Highest Hidden Costs in Construction
Available research indicates that the financial impact of rework remains significantly underestimated. According to data cited by Autodesk from the Navigant Construction Forum, direct rework costs typically account for between 4% and 6% of total project value. When indirect impacts such as schedule delays, management overhead, productivity losses, and operational disruptions are included, the figure approaches 9% of total project cost.
For a facility modernization project valued at $10 million, indirect and direct rework costs can represent hundreds of thousands of dollars in avoidable expenditures. Mechanical integration failures often contribute disproportionately because they affect interconnected systems rather than isolated components.
A misconfigured control sequence, for example, may require mechanical, electrical, automation, and operational teams to revisit completed work. A poorly coordinated equipment replacement can trigger modifications across multiple disciplines. What appears initially as a localized issue frequently expands into a project-wide coordination challenge.
The analysis concludes that successful turn-key construction depends less on equipment selection and more on the ability to coordinate mechanical systems within the broader operational environment of the facility.
According to a 2018 study by FMI and Autodesk, poor communication and data management are significant drivers of inefficiency in the construction industry. Rework attributable to these issues accounts for 52% of total rework, translating to an annual cost impact of $31.3 billion across the United States. The same study found that non-productive labor consumes 35% of all work hours, representing an annual labor impact of $177.5 billion. Complementing these findings, the Navigant Construction Forum estimates that direct rework costs alone account for 4 to 6% of total project cost, with the broader impact climbing to approximately 9% of project cost once indirect costs are factored in (Navigant Construction Forum; FMI / Autodesk, 2018).
Commissioning Delivers Measurable Performance Improvements
While construction-industry research highlights the cost of integration failures, federal research demonstrates that structured commissioning provides a reliable method for reducing those risks.
A landmark Lawrence Berkeley National Laboratory study published for the U.S. Department of Energy examined 643 commercial buildings across the United States and found that commissioning new-construction facilities produced median whole-building energy savings of 13%. The same study found a median payback period of 4.2 years.
The significance of these findings extends beyond energy efficiency. Commissioning serves as a verification process that confirms systems operate according to design intent while functioning properly within the facility’s existing infrastructure.
During commissioning, project teams validate equipment performance, controls integration, sequence-of-operations logic, system interactions, and operational readiness. Problems that might otherwise remain hidden until occupancy are identified and corrected before they become operational liabilities.
The LBNL analysis also found that commissioning costs represented a relatively small portion of overall project value compared with the performance benefits achieved. This finding reinforces the conclusion that commissioning functions primarily as a risk-reduction investment rather than a project expense.
For facility managers evaluating turn-key projects, commissioning represents one of the few integration safeguards with extensive federal performance data supporting its effectiveness.
Existing Facilities Often Achieve Greater Savings
Integration challenges are not limited to new construction. Existing facilities frequently experience performance degradation as building systems evolve over time through renovations, equipment replacements, and operational changes.
Lawrence Berkeley National Laboratory’s 2013 analysis of existing-building commissioning found median whole-building energy savings of 16%, with savings ranging from 10% to 30%. Notably, approximately 25% of buildings studied achieved energy reductions exceeding 30%. These results suggest that many facilities operate with significant inefficiencies created by integration issues that accumulate gradually and remain undetected during normal operations.
Mechanical systems may continue functioning while operating outside optimal performance parameters. Controls may no longer reflect current occupancy patterns. Equipment schedules may conflict with actual operational requirements. Sensors may provide inaccurate information to automation systems. Because these deficiencies often develop incrementally, they can remain unnoticed for years while increasing operating costs and reducing system reliability.
The analysis finds that commissioning provides a structured process for identifying and correcting these hidden integration failures before they generate larger maintenance or replacement costs.
Building Automation and Retuning Extend Integration Benefits
Mechanical system integration does not end when construction is completed. Long-term performance depends on the ongoing alignment between equipment operation, facility requirements, and building automation systems.
According to Pacific Northwest National Laboratory research conducted through the U.S. Department of Energy’s building retuning program, facilities that optimize controls and correct integration faults typically achieve energy savings ranging from 5% to 25%.
The program reports average energy-cost savings of approximately $0.185 per square foot annually, with simple payback periods ranging from 0.3 to 3.5 years. These findings illustrate the importance of viewing integration as a lifecycle process rather than a construction milestone. Mechanical systems operate within dynamic environments where occupancy patterns, production requirements, utility costs, and operational priorities continually evolve.
Facilities that maintain alignment between automation systems and operational needs tend to preserve performance gains achieved during commissioning. Facilities that neglect optimization frequently experience gradual declines in efficiency and reliability.
The analysis concludes that integration planning should extend beyond project turnover to include long-term performance verification and controls management.
Commissioning Costs Remain a Fraction of Potential Losses
One reason organizations defer commissioning is the perception that it adds unnecessary project costs. Federal research suggests otherwise.
According to research conducted by Lawrence Berkeley National Laboratory and the Building Commissioning Association, funded by the U.S. Department of Energy’s Building Technologies Office, the median commissioning cost for new construction projects declined to approximately $0.82 per square foot by 2018. That figure represents roughly 0.25% of the total construction cost.
When compared against potential rework expenses, operational inefficiencies, startup delays, and energy waste, commissioning costs remain comparatively small. The available evidence indicates that the financial consequences of inadequate integration substantially exceed the cost of implementing structured verification processes.
For facility engineers and project managers, the question therefore shifts from whether commissioning is affordable to whether the risks of skipping commissioning are acceptable.
Methodology
JDI Industrial Services synthesized publicly available findings from the FMI Corporation and Autodesk Construction Disconnected Report (2018), the Navigant Construction Forum as referenced by Autodesk’s 2024 construction-industry statistics analysis, Lawrence Berkeley National Laboratory’s Building Commissioning: A Golden Opportunity for Reducing Energy Costs and Greenhouse-Gas Emissions (2009, reaffirmed by the U.S. Department of Energy in 2018), Lawrence Berkeley National Laboratory’s 2013 existing-building commissioning research, and the Pacific Northwest National Laboratory Building Re-Tuning program. No proprietary survey or original research was conducted. All statistics were drawn from named third-party sources and reflect publicly available information current through June 2026.
Frequently Asked Questions
What does “seamless integration” mean in a turn-key mechanical project?
Seamless integration refers to the successful coordination of new mechanical systems with a facility’s existing infrastructure, utilities, controls, operational processes, and physical constraints. Integration extends beyond equipment installation and includes ensuring that HVAC systems, piping networks, automation controls, electrical systems, safety systems, and operational requirements function together as intended. Federal commissioning studies involving 643 commercial buildings found that projects using structured verification processes achieved median whole-building energy savings of 13%, demonstrating the measurable value of coordinated system integration.
Why do mechanical integration problems show up so often during turn-key construction?
Mechanical integration problems frequently emerge because existing facility conditions differ from assumptions made during planning and design. Construction-industry research from FMI and Autodesk found that 52% of rework originates from poor communication and project data issues. When documentation is incomplete or coordination among disciplines is insufficient, conflicts often remain hidden until installation, testing, or startup reveals them.
What should a turn-key contractor do before construction begins to protect existing systems?
Turn-key contractors should conduct detailed site investigations, verify existing conditions, document utility capacities, review automation-system requirements, identify operational constraints, and establish coordination procedures before construction begins. Early verification reduces the likelihood of downstream rework, which industry research estimates can account for 4% to 6% of project cost directly and approximately 9% when including indirect impacts.
What role does commissioning play in mechanical system integration?
Commissioning functions as the formal verification process that confirms mechanical systems operate according to design intent and integrate properly with existing facility infrastructure. Lawrence Berkeley National Laboratory research found that commissioning new construction projects produced median energy savings of 13% and achieved a median payback period of 4.2 years. Commissioning identifies performance deficiencies before they become operational problems and provides documented validation that systems are functioning correctly.
What questions should facility managers ask a turn-key contractor about integration before signing a contract?
Facility managers should ask contractors how they will verify existing conditions, how they will test control integration, how they will minimize operational disruptions, what commissioning procedures they will use, and how they will validate system performance after installation. Building owners should also request documentation regarding startup procedures, controls optimization, and long-term performance verification. Federal research indicates that structured commissioning and re-tuning programs can deliver energy savings ranging from 5% to 25%, making verification procedures an important indicator of project quality.
About JDI Industrial Services
JDI Industrial Services is a Westminster, South Carolina-based industrial mechanical contractor founded in 1997. The company provides turn-key mechanical construction, maintenance, installation, and industrial services for facility engineers, plant managers, and industrial operators throughout the Southeast. More information is available at https://jdiindustrial.com/service-types/mechanical-contractor/.
Media Contact
Contact: Kevin Nealey
Email: keviCheckn.nealey@jdiindustrial.com
Location: Westminster, SC
View original content to download multimedia:https://www.prnewswire.co.uk/news-releases/proper-mechanical-commissioning-cuts-whole-building-energy-use-by-a-median-of-13-jdi-industrial-services-analysis-finds-302811092.html
You may like
Technology
Amwell Receives Frost & Sullivan’s 2026 United States Technology Innovation Leadership Recognition for Technology-Enabled Care Platforms
Published
44 seconds agoon
September 5, 2026By
Amwell® is transforming virtual care delivery through its unified Amwell Platform, combining interoperability, clinical integration, and intelligent orchestration to improve access, efficiency, and outcomes.
SAN ANTONIO, Sept. 5, 2026 /PRNewswire/ — As healthcare organizations move beyond fragmented telehealth solutions toward connected virtual care models, Amwell is helping redefine how digital care is delivered at scale. Frost & Sullivan is pleased to recognize Amwell with the 2026 United States Technology Innovation Leadership Recognition in the Technology-Enabled Care Platforms industry for its ability to address healthcare fragmentation through a unified platform that connects patients, health plan members, clinicians, and partner ecosystems across the care continuum.
Frost & Sullivan evaluates companies through a rigorous benchmarking process across two core dimensions: strategy effectiveness and strategy execution. Amwell excelled in both, demonstrating its ability to align strategic initiatives with evolving healthcare needs while executing with flexibility, scalability, and measurable customer impact. “The combination of reliability, flexibility, and clinically integrated workflows positions the Amwell Platform as a strategic enabler for organizations seeking to reduce fragmentation, improve member engagement with covered programs, expand access to care, and create more connected healthcare experiences,” said Sagar Mukhekar, Industry Analyst, Frost & Sullivan.
Guided by a strategy centered on connected care, interoperability, and continuous, digital innovation, Amwell has positioned the Amwell Platform as an operating layer for next-generation healthcare delivery. Rather than relying on disconnected point solutions, the platform integrates technology, services, and clinical intelligence to orchestrate personalized care experiences across virtual primary care, urgent care, behavioral health, chronic condition management, and specialized digital programs.
Backed by 20 years of technology-enabled care innovation, more than 90 million covered lives, and over 38.7 million virtual visits, Amwell continues to help health plans and healthcare organizations modernize digital care delivery at scale.
“As healthcare becomes more digital, it risks becoming more fragmented. Health plans need more than point solutions. They need enterprise infrastructure, clinical integration, and an open platform that brings partners and programs together. Our vision at Amwell is that technology creates value when it improves access, engagement, quality, and efficiency, and produces measurable clinical and business outcomes. We’re honored by this recognition from Frost & Sullivan,” said Dan Zamansky, Chief Product and Technology Officer at Amwell.
Amwell’s enterprise scale includes supporting the digital transformation of the Defense Health Agency’s Military Health System, serving approximately 9.6 million beneficiaries. The company’s commitment to measurable outcomes is also reflected in a landmark National Institute of Mental Health (NIMH)-funded study, published in Nature Human Behaviour and among the largest studies of its kind. The study found that students offered SilverCloud® by Amwell® engaged in mental healthcare at more than double the rate of traditional care, experienced lower rates of mental health disorders, and generated an estimated $1.18 million in avoided costs for the study population.
The company further differentiates its platform through intelligent orchestration and navigation, helping guide members to appropriate programs while giving clinicians visibility across care plans. Amwell also evaluates integrated third-party programs for clinical effectiveness, scalability, and enterprise readiness.
Frost & Sullivan commends Amwell for setting a high standard in competitive strategy, execution, and technological innovation. The company’s unified approach to digital care is helping reduce fragmentation, improve access, strengthen operational efficiency, and support more equitable and sustainable healthcare delivery.
Each year, Frost & Sullivan presents the Technology Innovation Leadership Recognition to a company that demonstrates outstanding strategy development and implementation, resulting in measurable improvements in market share, customer satisfaction, and competitive positioning. The recognition identifies forward-thinking organizations that are reshaping their industries through innovation and growth excellence.
Frost & Sullivan Best Practices Recognition
Frost & Sullivan’s Best Practices Recognitions honor companies across regional and global markets that exhibit exceptional achievement and consistent excellence in areas such as leadership, technological innovation, customer experience, and strategic product development. Each recognition is the result of a rigorous analytical process in which Frost & Sullivan industry experts benchmark performance through comprehensive interviews, deep-dive analysis, and extensive secondary research. The goal is to identify true best-in-class organizations that are driving transformative growth and setting new industry standards.
Contact us: Start the discussion.
Contact:
Ashley Shreve
E: ashley.weinkauf@frost.com
SOURCE Frost & Sullivan
Technology
MiniTool Released MovieMaker 8.9 with Advanced Keyframe Animation
Published
45 seconds agoon
September 5, 2026By
VANCOUVER, BC, Sept. 4, 2026 /PRNewswire/ — MiniTool Software Limited has released MiniTool MovieMaker 8.9, a significant update to its video editing software. The latest version focuses on empowering creators with advanced keyframe animation controls, a more streamlined installation experience, and an optimized export button for a smoother experience.
Precise Control with Keyframe Animation
The hallmark of MiniTool MovieMaker 8.9 is the introduction of keyframe animation for video, images, and elements. Users can now set keyframes for position, scale, and rotation at different points. As a result, they can easily generate smooth, cinematic motion effects.
The position parameter supports accurate X- and Y-axis adjustments, allowing flexible horizontal and vertical movement of clips to achieve natural screen scrolling and displacement effects. The scale feature allows for seamless zoom-in and zoom-out transitions, enabling users to zoom in on a clip and highlight key visual elements. Coupled with rotation control, which supports precise angle adjustments, the three tools work together to deliver smooth, dynamic visual effects.
Designed with simplicity and accessibility in mind, this update brings intuitive keyframe animation tools without complex settings. It balances powerful editing capabilities and ease of use, allowing users to easily bring static photos to life and create custom movements for high-quality visual content.
Installation Package Optimization for Faster Setup
MiniTool MovieMaker 8.9 places a strong emphasis on the installation package. In this latest release, the development team has reduced the overall installation package size, enabling a faster, more streamlined download and setup experience. This enhancement not only saves disk space but also improves application launch speeds. As a result, creators can quickly run the software and start working on their projects with minimal delay.
Enhanced Export UI for a Seamless Final Step
The final export stage is crucial to the editing workflow. This time, MiniTool MovieMaker 8.9 brings a new export button with a redesigned interface. This update optimizes the export button and provides intuitive guidance. Therefore, users can quickly locate the button for exporting their projects, whether they are absolute beginners or experienced editors.
About MiniTool MovieMaker
MiniTool MovieMaker is an easy-to-use video editing program designed for beginners, featuring a clean interface and a variety of effects, text templates, stickers, filters, and transitions for quick video creation.
The software offers a flexible multi-track timeline where users can layer and independently manage video tracks and audio tracks to create complex compositions, such as picture-in-picture (PiP) effects and video collages. Users can also place visual elements on different layers and lock tracks to prevent accidental edits.
More importantly, this editing tool can export videos in 1080P or 4K for free and without watermarks, ensuring high-quality, professional-looking results.
About MiniTool® Software Ltd.
MiniTool® Software Ltd. is a software development company specializing in providing software services across multiple fields, including video editing, screen recording, video conversion and compression, video enhancement, as well as disk partition management.
View original content to download multimedia:https://www.prnewswire.com/news-releases/minitool-released-moviemaker-8-9-with-advanced-keyframe-animation-302869995.html
SOURCE MiniTool® Software Limited
Technology
From Trust to Value: Miles Group Signs Bo Jin and Isaac Lam, Launching into the Athlete Representation Track
Published
49 seconds agoon
September 5, 2026By
HONG KONG, Sept. 5, 2026 /PRNewswire/ — Miles Group, specializing in international sports marketing, announced today the signing of two outstanding professional golfers, Bo Jin and Isaac Lam. This milestone concurrently marks the official launch of the company’s athlete representation business.
Founded in 2012, Miles Group has spent over a decade providing Asian market marketing services for premier global golf brands, including Major Championships, the LPGA Tour, and the United States Golf Association (USGA). In 2026, the group’s domestic arm, Miles Shanghai, launched its proprietary tournament IP—the Junior Charity Classic—which offers top Asian junior golfers a direct pathway to elite junior tournaments in the United States.
“I have always believed that elite athletes are among the rarest and most valuable brand assets, yet their commercial potential remains vastly underestimated. Miles Group is entering the talent representation arena not simply to sign established names, but to leverage our 15 years of international sports marketing expertise. Our mission is to build a dedicated value-amplification system for Asia’s athletes, empowering them to command top-tier commercial influence far beyond the field of play.” said Smile Xu, founder of Miles Group and a top-tier marketing strategist.
“Having known Smile for ten years, I’ve watched her grow from an industry rising star into someone who drives real change. I have absolute faith in her capabilities, but what I admire most is her vision—helping more players use innovative methods to unlock true, long-term value, and even rewrite the rules of the industry,” said 24-year-old Bo Jin, who currently competes on the China Tour. “Entering my second year as a professional, I chose Miles Group because I believe in the future she sees, and it’s a future I want to be part of.”
Bo is the first Chinese player to reach the finals of the U.S. Junior Amateur, a member of the 2019 Junior Presidents Cup International Team, the individual runner-up at the 2021 NCAA D1 Championship, and the runner-up at the 13th Asia-Pacific Amateur Championship in 2022. Turning professional in 2025, Bo delivered a remarkable rookie year, capturing two runner-up finishes on the China Tour and placing in the top 20 during his DP World Tour debut.
Isaac Lam, 27, hails from Hong Kong, China, and turned professional in 2024. Now an active competitor on the China Tour, he boasts the title of a two-time Tour champion. Following his maiden China Tour victory at the 2025 Wuyishan International Open, Lam lifted his second trophy this past August at the Fanling Golf Classic in front of his home crowds.
“On the course, I am a champion, but in the business world, I am a complete novice. Two China Tour titles didn’t bring the commercial breakthrough I had anticipated,” Lam shared. “Since my amateur days, Smile has always given me unconditional advice. Joining Miles Group now is a choice born from seeing her selfless dedication to young players. She brings both the wisdom to sharpen my direction and the resources and capability to translate a championship title into real commercial value.”
Play Beyond • More than just the game—from amateur to professional, from trust to value! In launching its talent representative agency business, Miles Group is dedicated to systematically developing athletes’ multidimensional commercial value off the course. Moving forward, Miles Group will leverage precise resource matching and long-term strategic planning to create sustainable growth opportunities for players, while introducing high-value sports IPs to partners for mutual empowerment.
About Miles Group
Miles Group is a marketing agency headquartered in Hong Kong that has been deeply rooted in the Asian market for 15 years. With teams across Mainland China, South Korea, Japan, Singapore, Malaysia, India, and Thailand, it focuses on the sports and lifestyle sectors. The group provides one-stop services covering public relations, digital media, content creation, KOL management, and event management for top global clients. Its client portfolio includes industry benchmarks such as USGA, LPGA, LIV Golf, BLAST and more. Since 2025, the group has focused on developing its own tournament IPs and content; its inaugural Junior Charity Classic immediately became an industry market benchmark. 思迈超牛 is the affiliated operating company of Miles Group in Mainland China.
View original content:https://www.prnewswire.com/apac/news-releases/from-trust-to-value-miles-group-signs-bo-jin-and-isaac-lam-launching-into-the-athlete-representation-track-302870107.html
SOURCE Miles Group
Amwell Receives Frost & Sullivan’s 2026 United States Technology Innovation Leadership Recognition for Technology-Enabled Care Platforms
MiniTool Released MovieMaker 8.9 with Advanced Keyframe Animation
From Trust to Value: Miles Group Signs Bo Jin and Isaac Lam, Launching into the Athlete Representation Track
Send Rakhi to UK swiftly with UK Gifts Portal
Whiteboard Series with NEAR | Ep: 45 Joel Thorstensson from ceramic.network
New Gooseneck Omni Antennas Offer Enhanced Signals in a Durable Package
Why You Should Build on #NEAR – Co-founder Illia Polosukhin at CV Labs
Whiteboard Series with NEAR | Ep: 45 Joel Thorstensson from ceramic.network
NEAR End of Year Town Hall 2021: The Open Web World, MetaBUILD 2 Hackathon and 2021 recap
Trending
-
Technology2 days agoOnymos and Vanta Diagnostics Collaborate to Scale Intelligent Lab Intake
-
Technology5 days agoMOEA’s DoIT Showcases 31 Innovative Technologies at Meet Greater South
-
Technology3 days agoOWASP GenAI Security Project Releases 2026 Top 10 for LLM Applications, Debuts Agent Control Standard and New Resources for Securing Generative and Agentic AI
-
Technology2 days agoOMVP Backs Europe’s Sovereign Space Future as American Lead on €50M+ HyImpulse Financing
-
Coin Market3 days agoFake Claude desktop app spreads crypto-stealing malware
-
Technology2 days agoNew research proves mutant AI swarms outperform optimized models in a changing world
-
Near Videos4 days agoIllia Polosukhin: The Case for User-Owned AI
-
Coin Market3 days agoDoes the Bitcoin rally mean we haven’t wasted our lives in crypto?